Minimum Level is also known as buffer stock level, safety stock level.the lowest amount of a product that you can have in stock and still be able to meet customer demand.
When inventory balance falls below this level, production functions could be disrupted and the company may fail to deliver the product on due time.
At this stage, the business entity should reorder the materials considering the probable lead time. Lead time is the expected time period of delivery of goods to the customer’s warehouse or at the production point.
Maximum usage x Maximum Lead Time – Average rate of consumption x Average Lead Time or.
Minimum Level of Inventory = Reorder Level – (Average rate of consumption x Average lead time)
ADVANTAGES OF MINIMUM STOCK LEVEL
1. Helps avoid running out of a product, which could lead to lost sales
2. Reduces the holding cost of the company. Holding costs include utility costs, labor costs and other costs associated with to hold the materials in the store
3.Reduces the chances of losses, defective, etc. due to always monitoring.
4. Reduces the pressure on cash flow for purchasing excess raw materials
CONSIDERATION WHEN SETTING MINIMUM STOCK LEVEL
1. Determine the average rate of consumption
2. Average rate of consumption. Lead-time i.e. time required for replenishment
3.sourcing of materials. The lead time of materials will vary in the case of the local market and foreign market. Lead time of foreign purchases will be longer than the local market.
4. Minimum, Normal and maximum rate of consumption to determined
Worked out example
Chunks Groups sells equipment for production which cost 300 and are sold at 500. Maximum demand is 300,000 per year and average demand is 240,000 per year the average lead time is 60 days maximum lead time is 67 days, compute the minimum stock level
Minimum Stock Level = Re-order Level – (Average Demand x Average Lead Time). First calculate the Re-Order level
Maximum daily demand = 300,000 ÷ 365. = 822 units per day Average daily demand =. 240,000 ÷ 365 = 658 units per
Re-Order level = Maximum demand × Maximum Lead Time. 822 × 67. = 55,074 units
Minimum Stock Level Reorder Level – (Average Demand x Average Lead Time. 55,074 – (658 × 60). 55,074 – 39,480. = 15,594. Units